A start-up company needs to quickly expand its product portfolio to meet market demand. Recently, staff members are working on two or three agile teams, each dedicated to a different product line. Output is dropping and defect rates are rising in all teams. In which two ways can the project manager help the agile teams improve their work? (Choose TWO). |
The agile team surpassed the planned number of stories in the last three agile iterations. How can the project manager be sure all the work performed is truly complete? |
A medium-sized company is expanding into a new market. However, the company does NOT have previous experience in that market. A project manager needs to collect requirements. Which two tools or techniques should the project manager use? (Choose TWO). |
A client brings a project manager into a project during the project’s execution stage. The project manager reviews the project scope for cost estimating purposes and notices that some deliverables were missed in the work breakdown structure (WBS). Which step should the manager take next? |
Review the following project characteristics: – A sponsor approves a project. – The project manager invites selected team members, key stakeholders, and the sponsor to a meeting. – The primary purpose of the meeting is to create a document that will guide the team in defining the main project deliverables. What will be the final output of this meeting? |
A project manager is working with a customer who repeatedly submits requests for new requirements for an existing software product. The project manager has already provided the completed scope definition for the product’s next version release to stakeholders. Which step is appropriate for the project manager to take next? |
A project manager is working on a software development project. Two customers are repeatedly submitting new feature requests. The completed scope definition for the product’s next version release has already been provided to stakeholders. What should the project manager do next? |
An empowered agile team showed impressive progress in the first four iterations, but now the product owner has noticed low output in the latest five iterations without any apparent reason. What could be the cause of this situation? |
An agile team is struggling to solve a blocking issue with packaging design. Eventually, they find a solution, but it requires a different product format. What should the team do before further developing the solution? |
A merger of two companies results in combining an agile software project and a predictive electronics project into a single hybrid project. Two months later, requirements have changed in both tracks but NEITHER has a full picture on status or importance of the requirements. How can the project manager best resolve the problem? |
A marketing team is developing a new website for an existing product range. The team reads through some customer comments submitted on the current website:
“Too much clicking!” Which tool or technique should the marketing team use to identify the target audience’s style preferences? |
A project has the following characteristics: – To determine what product should be created, a feasibility study was conducted. – A change request was approved to develop another product that contradicts the original requirements. – Data analysis was conducted before the change request was approved. Which action should the project manager take? |
User test results for a prototype release are ready. The test users describe the kind of smoother experience they want, the many missing features they desire, and the ways the product could be more visually appealing. What conclusions can be drawn from the user’s input? |
During estimating, the team is discussing an item in the backlog. It becomes clear that the item can be done in different ways, but the best way is NOT obvious. What should the team do to progress on this item? |
The agile team is building a version of a smartphone shopping application suitable for older people. Marketing has not been able to find any volunteer test users fitting the profile. Which option would be most effective to ensure the best product value is delivered? |
A customer contemplates adding new features to a project deliverable. Which mandatory step must a project manager take before a project team member can start working on these new features? |
A client’s employee asks the project manager for an additional, new product feature during a status meeting. To which document should the project manager first refer to determine who has the authority to approve this request? |
A project is 50% completed. An essential project team member requests two (2) months leave for personal matters. What should the project manager do first? |
A project sponsor asks the project manager to change production materials because these materials could cause health problems to consumers. Which step should the project manager take? |
A team was in the execution stage of the project management plan when three (3) necessary changes were brought to their attention. The team members all have differing opinions regarding how to implement the changes. What should the project manager do? |
A project manager recently joined a new project with the following characteristics: – Tight deadlines – Global virtual team – Fixed budget During the planning stage, the project manager wants to avoid scope creep and keep the team focused on delivering a product that meets requirements. The project manager should ensure __________. (Fill in the blank with the correct response.) |
The project sponsor requests that an element of a product will be swapped for the equivalent supplied by a local manufacturer in order to have a more sustainable supply chain. Which action should the project manager take? |
A worldwide product launch will likely be delayed by the lengthy analysis needed to assess the impact of new European Union (EU) regulations. Perishable ingredients and factory bookings are at risk of being lost. The executive committee decides to postpone the launch in the EU but maintain launch dates in all non-EU countries. How should the project manager re-plan the project to support both launches? |
A multi-year, hybrid pharmaceutical project adds new fixed-date activities for the team to run Machine Learning (ML) processing of medical scans. The output from the ML analysis is used by an agile team of doctors to determine next steps in a patient case. The project manager has updated the scope statement and schedule. In which three other documents should the project manager record this new process? (Choose THREE). |
A project’s workload is increasing significantly, and the resource level is NOT sufficient. In response, management outsources some major tasks to keep the project on schedule. What should the project manager do in this scenario? |
A textile development project needs a specialized resource to work for 900 hours. The company has decided to outsource these hours. Because of internal policies, all potential service providers must be given the same information about the requirements. Which action should the project manager take to ensure this? |
Because a deliverable does NOT meet the agreed-upon quality specifications, it is rejected by the customer. Team members find that the deliverable fails to meet expectations because of a problem with vendor-provided parts. The vendor says that they will NOT correct the problem. Before deciding on next steps, what should the project manager do? |
Near the end of a manufacturing project, several team members are transferred to another project. To complete the work, the project manager needs to acquire additional resource support from a new supplier but is concerned about the cost risk of using a new supplier at this advanced stage of the project. Now, the project manager needs to work with the procurement team to establish specifications and type of contract to be used. What should be done? |
A deliverable does NOT meet the agreed-upon quality specifications and is rejected by the customer. After investigation, the project team finds a fault with the vendor-provided parts. This fault caused the issue. The vendor says that they CANNOT correct the situation. What should the project manager review before deciding on next steps? |
A hybrid project combines IT integration and software development tasks. The predictive and agile teams seem to be working in silos, resulting in misaligned deliverable scheduling. Which two measures would most effectively enable the teams to better synchronize their deliveries? (Choose TWO). |
Company G has a goal of increasing customer satisfaction within four (4) months and initiates a project to meet this goal. The project manager needs to identify best practices. Which method should the project manager use to accomplish this? |
A project manager begins to prepare the project management plan after receiving the project charter. There is currently NO historical information in the project management office (PMO). What next step should the project manager take in this scenario? |
Company P’s IT transformation project has three (3) deliverables, and they have the following characteristics, according to the project team: – Deliverable 2 has strictly scheduled milestones, with no expected variation in the timeline. – Requirements for deliverables 1 and 3 will change quickly during development. Which project life cycle should the project manager use for this project? |
A consultant has advised an IT director to use a development and operations (DevOps) approach to a migration project. The IT director wants to understand how the necessary speed can be achieved in a safe way.
Which two examples could demonstrate how DevOps can reduce incidents and speed up deployment at the same time? {Choose TWO.) |
An innovative product fails to satisfy targeted consumers despite significant investments in quality control and marketing campaigns.
Which agile practice would best prevent future failures of this nature? |
An emergency vaccine roll-out project should be deployed to vaccination centers as soon as confirmed locations are booked. Factors such as delayed batch shipments, safety protocols, and target age groups may block the deployment at the last minute. However, the deployment process does NOT vary after passing the tollgate to begin setup at a new location.
Which project approach would best support the goal to maximize the number of centers deployed? |
A project to start building an ecology-focused resort complex is planned, and the contract is ready for signature. The client now asks the prime contractor to suspend planned development work on a parcel of land while the team runs a consumer study—the team needs to know what kind of structures to build on the parcel.
What should the prime contractor do to quickly close the deal, given the new client requirements? |
A new wildlife reserve project will have a staff of approximately 80 experts, builders, and logistics workers with exposure to various safety risks. The project manager wants a scalable approach combining flexibility and team dynamics with traditional safeguards.
Which option could be used to tailor a hybrid project of this nature? |
In a hybrid product design project, the team encounters a 3D printer malfunction resulting in costly losses of titanium supplies. When the production team tells the agile programming team about the problem, it becomes clear that mistranslated data sheets created problems for both teams. However, the agile team resolved their problems a month before the malfunction.
What could the agile team have done to prevent the current malfunction? |
A medical equipment vendor is running a hybrid project which includes some custom software development by an agile team. The team progress is good, but slow customer approval causes unnecessary delays. The customer insists that approval can only be given after repeating all the test cases in the target environment.
How can the project manager accelerate the approvals and build customer trust at the same time? |
An organizational change program has met with internal resistance, a risk which was previously identified. A logistics manager is particularly affected, due to reduction of the team size and the rate of change driven by an agile planning of the predictive implementation. The manager’s supervisor formally requests the change program to delay implementation for the logistics team.
What should the project manager do next in response to this request? |
A project team collected sensitive client data during the early stages of a project to help develop the project management plan. The team is now working on deliverables for the project when the compliance manager discovers a data breach and alerts the team to a compliance issue. Which document should the project manager review first? |
The team working on Project A has resolved a technical issue, and the project is moving forward. The project manager has been warned that the same issue will probably arise on similar projects in the future. What should the project manager do first when responding to this warning? |
While reviewing the issue log, the project manager notices that tasks assigned to two (2) team members are quite a bit behind schedule. What should the project manager do? |
Project team members are busier than usual. They indicate that they do NOT have the time to update the lessons learned repository because of other project responsibilities.
How should the project manager respond? |
A large project includes functional groups in four (4) countries, a steering committee, and a project sponsor. As the project approaches completion, the project manager must prepare the closeout documents. How should the project manager obtain appropriate signoff on the acceptance of project deliverables? |
After six (6) iterations, significant variations have occurred to project scope and schedule. These are due to the customer’s technology regulations and security policies, which are regularly reviewed. The project manager suggests taking a new approach to the next iteration to avoid possible delays. What should the project manager do first? |
A project manager has completed the following steps: – Finished a major IT deployment project – Confirmed with the release manager that all systems are working – Confirmed that functionality has been verified by the quality assurance team – Informed the customer Which next step should the project manager take? |
Review the following steps.
1. A project has been successfully delivered. What is step 3? |
Review the following project characteristics:
– The project is in the initiation phase. What is the first action the project manager should take? |
After a project ends, the project manager and project team members are still being asked to do the following: – Evaluate new requirements – Make minor modifications – Solve technical issues The project manager wants to ensure the product or service developed by the project now has operational support. What should the project manager do? |
Project team members are spending a lot of time helping maintenance and operations staff with a recently commissioned project component. The project manager needs to validate that the component was signed off and ownership transferred. Which three (3) documents should the project manager use for this decision? |
A project is completed, but the project manager and project team members are being asked to do the following:
– Troubleshoot and resolve technical issues The project manager needs to ensure that the product developed by the project now has operational support. What should the project manager do? |
At the end of an agile project, all stories are completed on schedule and all tests passed, but the customer does NOT consider the product a success.
Which is the most effective way to prevent this outcome in future projects? |
An energy infrastructure vendor is delivering a complex solution proof of concept to a new strategic customer. The predictive project should be completed in 10 weeks, but there will be a long list of outstanding items, and some are dependent on external events with uncertain scheduling.
How should the project manager handle the outstanding items? |
A project has the following characteristics: – It is in the execution stage. – A new law requires immediate compliance. – This law will impact the project’s scope, schedule, and cost. What are three possible actions to ensure compliance? (Choose three) |
A new law is expected within the next 6 months that will affect a business’ product line. The next product is launching and should be completed within 3 months. Unfortunately, the new product will NOT meet the requirements of the proposed law. How should the project manager respond to this potential problem? |
Project N is a business merger in a highly regulated industry. The project sponsor and a high-level executive have asked for changes that appear to disregard legal requirements. What should be the first step in the project manager’s response? |
A project manager needs to ensure that all data security requirements are covered during a data warehouse development project’s execution phase. Each of the databases created during different project phases will have a specific data security policy to comply with governmental data security laws. How should the project manager plan to meet these requirements? |
A project team learns about a new compliance requirement from an international entity that may impact the baseline business case for the project. They learn this right after the project charter is completed and the project sponsor has signed. How should the project manager proceed? |
A Canadian start-up company announces to the press its imminent launch in the European Union (EU) and Latin America. Soon afterward, the compliance team recommends delaying the launch by 6 months to avoid substantial penalties related to a new set of EU regulations. Which approach could the project manager take to advance the launch project while preparing the compliance measures? |
Two (2) months into a 3-year mobile telecom roll-out, the project manager discovers that approximately fifteen percent (15%) of the equipment is prohibited for delivery because of an embargo. The procurement contract does NOT cover the embargo case, but the company could incur severe penalties for incomplete delivery. What is the appropriate solution for the situation? |
The legal team informs the product owner that another company owns a patent for an innovation used in the agile team’s product, which is now 75% complete. What should the product owner do to determine the appropriate way forward? |
A new regulation requires consumer warnings on labels, but a company’s product package is too small to fit the additional information. The regulatory specification does NOT provide a solution, so the agile team decides to solve the problem by displaying the information on a fold-out flap. The start of mass production of the new labels, the project’s next milestone, is scheduled to begin in five days. What should the agile team do next? |
A project manager leaves the company and is replaced. The new project manager is excited to start guiding the team toward project success. What should the new project manager do first? |
A project manager receives the following for a new project: – Assumptions – Restrictions – Preliminary scope After receiving this information, what should the project manager do first? |
A week prior to the project kick-off call, a project manager meets with a key project resource to gain a deeper understanding of the complexity of the project deliverables. The resource expresses concern and worry regarding the deliverables. How can the project manager ensure that the deliverables are realistic? |
A key project resource is discussing the complexity of project deliverables with the project manager 2 weeks before the kickoff call. The resource expresses nervousness and concern regarding the deliverables. The project manager wants to ensure that the deliverables are realistic. What is the appropriate action to take? |
During user testing, a client agrees to the final product. One day later, the client indicates that the final product MAY NOT be acceptable. What should be the project manager’s first step for resolving this issue? |
A new product development project is to be initiated in a difficult business context. Competition is driving prices down, and supply costs are rising. Why would an agile incremental project approach be the safest choice in this context? |
The marketing director is displeased that the agile innovation team is producing too many novelty products with too little business value. Which two approaches should the project manager take to correct the team’s approach? (Choose TWO). |
An agile innovation team is highly productive. However, the Head of Operations informs the product owner that the company is NOT getting sustainable return on investment from the team’s work. How should the product owner address the problem? |
The success of an ongoing agile project is measured as follows:
2-week Stories Stories Planned Earned 1 15 10 450K 300K |
A company is losing market share to disruptive competitors with new business models. A cross-functional agile team has been formed to recommend ways to recover market share. How can the team increase their chance of producing successful recommendations? |
Over the past six months, the development cost per story has risen by more than 250% due to a faulty platform which is NO longer supported. The product vision highlights unique features of the platform as a pre-requisite for the product. What should the project manager do to determine next steps? |
The agile team will take over from another supplier to maintain a client’s website. The team notices that recent browser changes imply that most of the website’s existing content would now require users to install a plug-in. How should the agile team move forward? |
The quarterly results show that competitors are driving prices down. The company is losing market share and midway into a product development project, it appears the sponsoring unit is not likely to get return on their investment. Which two actions should the project manager take to adapt the project to these new conditions? (Choose TWO). |
A pharmaceutical project includes an agile team of doctors who analyze human tissue scans from drug trial patients. The CEO wants to leverage Machine Learning (ML) technology, because it is proven to be faster and more accurate than doctors in scan analysis. How should the product owner proceed in response to the CEO’s wish? |
As part of an organizational change program, an experienced project manager with agile experience and certification is hired by a company with a strong predictive culture. Which two actions can the project manager take to start helping the company adopt agile methodologies? (Choose TWO.) |
An agile team needs to decide who should represent them in the Scrum of Scrums. Which option should be used to select the best-suited team member? |
A project manager for a major annual international sporting event is reviewing data collected after the second of six planned project phases and sees that the team is performing poorly. The project uses a hybrid management model, with a project manager and decentralized decision-making at the team level. The project manager learns that several critical elements are behind schedule, and some delivered services are not operating correctly, resulting in rework and more delays. Also, team members might be enjoying working with the sports teams and being in the media spotlight a bit too much.
|
A large project team for a major annual event is reforming with all the same team members. To prepare for the preliminary meeting with the team, the newly assigned project manager reviews the lessons learned repository and sees this highlighted comment: “Team members were distracted at the live matches. The team leads were ineffective at redirecting team member effort.”
How should the project manager approach this situation? |
To prepare for this year’s major international sporting event which will be broadcasted live on every continent, the project manager arranges professional media training for key members of the project team and stakeholders. Stakeholder A, who is outspoken and extremely active in the media, is not taking the training class seriously. The facilitator reports the issue by email, stating “I can’t work with this trainee anymore!”
What should the project manager do? |
Owners of a small luxury travel magazine want to expand their services to provide bookings for readers’ dream holidays. They commit 15% of the company’s annual profit over 3 years to develop and launch the service. The company creates a high-level vision statement and objectives and key results (OKRs), which they hand over to a consulting company.
Which approach and initial scope decision is suitable for this project to begin work? |
A government agency is concerned about the continuity of their projects. Many senior staff members who started the agency are retiring in the next 5 to 10 years. Their knowledge and experience as project managers of past and current projects will be critical to the agency’s future success.
A project manager is engaged to steer the effort. Which two options are the best ways of ensuring knowledge transfer for continuity of the agency’s projects? (Choose two) |
A company designs robotic vacuum cleaners. Sales are declining, so the company wants to pursue a business opportunity in a growing market: to adapt their machinery with artificial intelligence (AI) for use as home companions. A senior business analyst completes a feasibility study and examines the opportunity, delivering three main points:
• Partner with another company to provide AI technology instead of in-house capability development The stakeholders authorize the project unanimously and appoint a project manager to start work. Which two actions should the project manager perform first? (Choose two) |
An agile project team previously attempted to launch a new version of streaming fitness videos in an increasingly competitive market. By the end of the last project, competitors had already launched similar products. Stakeholders were disappointed about the loss of value.
Which two actions should the team leadership have taken or done differently to avoid stakeholder dissatisfaction? (Choose two) |
A project team working in a city’s transportation agency is planning the launch of a 24-hour subway service for the first time in its 120-year history. One month before the launch, a terrible electrical accident shuts down service for the whole city, causing injuries and millions of dollars of damage to the infrastructure.
What should the project manager do? |
A project to train kitchen personnel in process efficiencies for a restaurant franchise has a small project team of four people. It is essential that this team has a broad understanding of the franchise’s business processes so they can create training that delivers the efficiencies required across the business.
Which team member already has T-shaped skills that would be beneficial to this project? A – Project manager with 30 years of experience leading business development projects |
At the beginning of a customer service improvement project, two stakeholders are noted as “resistant” on the stakeholder engagement assessment matrix (SEAM):
• A finance executive who says the cost of the project is too high All other stakeholders support the project. After months of difficult negotiations, the customer care stakeholder group is now noted as “neutral,” though final agreements must be signed; this is ongoing and will take significant time and effort. The finance executive continues to state that the cost of the project is too high. What should the project manager do? |
An agile team member has an extremely varied skill set and performs their work well on projects. This team member has been allocated to many different roles during their work history at the company. For this reason, the team member states, “I feel like I am put on projects randomly. I am not getting anywhere, and the company does not value my work.”
What should the team lead do? |
An established farm is struggling to maintain profitability and plans to integrate an agro-tourism project to expand the business. They hire a project manager and personnel and initiate a project. The new team members will be shared resources for both the farm and the playground project. The farm needs to continue generating cash flow to support operations until the project is integrated–in 8 months.
By the second month, the project manager learns that farm production performance has decreased drastically because the project takes up a lot of the team’s time. Which two approaches should the project manager consider to provide the best chance for the business to succeed and produce the desired outcomes? (Choose two) |
A company is undergoing a global enterprise-level transformation. In 3 years, they will end 85 years of publishing books and instead offer tutored, virtual learning communities.
The first big project is to refit the factories and warehouses as film studios. The project management office (PMO) authorizes a project using a predictive life cycle, and that work begins. However, the learning community designers (key stakeholders) keep requesting design changes, which has caused delays and costly rework. With 18 months left, the team is getting nervous. How should the project manager respond? |
During a busy period of organizational change, team members on project L are allocated as follows:
• 60% of working hours – project L Project L is progressing according to schedule and budget, but a few minor quality factors are being neglected. The project manager is prioritizing on-time delivery and the very dedicated team asks about working overtime to improve quality. How should the project manager respond? |
A hotel chain wants to improve the customer loyalty program by increasing the number of returning guests by 35%. The project manager finds two strong opinions:
• Stakeholder J suggests that the sales teams focus on the top 10 corporate clients and incentivize them toward exclusive use of this hotel chain • Stakeholder M suggests improving the quality of their airport sites, which already have a large number of repeat guests. Stakeholder M also insists the chain cannot compete in larger markets, so the strategy stakeholder J suggests will fail. In a dramatic escalation, stakeholder M sends an email to the project manager and the entire leadership team accusing stakeholder J of having a bias. What should the project manager do first? |
At the start of a project, stakeholders agreed to expedite approval of the project charter and project management plan to get the project started on time. But after the first sample batch is sent to the customer, a serious problem is discovered:
Customer: “Samples sent over for approval are inferior, with failure rate of 27%. . . thought we agreed 15% as maximum failure rate.” The project manager checks the project management plan and discovers that “good quality” was noted as the acceptance criteria instead of the usual number range for failure rate. The other stakeholders are willing to approve the batch with a 20-25% failure rate, but the customer rejects this idea. What should the project manager do, and which artifact should be updated? |
A project that is in progress requires a resource with a specialized skill. Because of time limitations, the agile team has two options: either borrow a team member from another department who can work part-time or use an independent contractor. The eight team members discuss the options, but they are unable to reach an agreement. The vote is 50/50, and both options have positive benefits as well as risks.
What should the team do? |
A project will create digital keys for 18,500 employees at an airport. The project management plan states that security clearance data for employees must be verified and updated in a digital security file every 6 months. This is part of the acceptance criteria. In month 3, the project manager discovers that the company hired to maintain the digital security files has filed for bankruptcy.
Which statement describes the status of this project? |
A pharmaceutical company has manufactured its best-selling product for more than 50 years. Production has steadily increased, and the company is ready to make a significant investment to expand the business.
Leadership asks the project management team to carefully assess the risk of this expansion. What should the team focus on? |
A financial services project will be executed by a team of three teams. Each team has unique objectives for the first phase and then will merge efforts for the second phase to deliver the product. The product owner wants it done as soon as possible. In the initial draft of the schedule, team A finishes their work in a 9-week time line, but teams B and C need 14 weeks to complete their work.
The scrum master suggests allocating resources from team A to teams B and C during weeks 10-12, to shorten the total time line. Teams B and C agree and would like the added resources. However, team A says “no” because they need to prepare the transition plan and train staff on the product during weeks 10-14. Which two actions should happen? (Choose two) |
A project manager in a luggage manufacturing company is asked to explore new business opportunities and deliver three proofs of concepts (POCs) to the executive team. Sales are declining rapidly and the company’s future is at risk. The 15 project team members are stakeholders from all over the organization, chosen for their independent thinking. They have very different points of view about which opportunities are best, and arguments are erupting openly and often.
Because of the varied points of view, the project manager adopts an agile approach to quickly build shared understanding about the work and find the best solutions to present to the executive team. Which two approaches should the project manager consider? (Choose two) |
A virtual team will travel to a work site and work as a colocated team for 6 weeks in Q3 of next year to transition their project to the customer. One team member, whose role is critical to the transition, is getting married during Q3 but has not told anyone until now. This team member requested 3 weeks of holiday right before the planned team travel.
What should the project manager do? |
There have been many disputes on the project with the current contractor. The contractor claims the project team is always asking that work not be listed in the contract, and the team claims that the contractor has not been doing the work listed in the contract. What should the project manager do first?
The project manager and team have decided to hire a contractor to complete the installation of the servers for the system’s upgrade project. The terms of agreement have the contractor being paid on a monthly basis until the work is done. What process will the contractor payments be made in?
While working on a project, the CEO of the company has informed you that he would like to terminate the project and have you work on a few others projects. What kind of influence does this best represent?
Which of the following statements is true about projects:
The project manager has brought the project team together to explain what the project will be about and what their roles will be. The team members introduce themselves to each other and learn about the different skill sets each of them brings to the project. What stage on Tuckman’s ladder best represents this?
The project team has completed a major deliverable on the game development project. The deliverable was given to the project manager. What action should the project manager take next?
The team is concerned with the quality of the product about to be created by the project. What statement about quality management is true?
While managing a datacenter development project, the project manager has noticed there are many conflicts between the team members on the project. When managing a conflict in a project, what would be the best role for the project manager?
The project team has completed a bidder conference for the office renovation project. Over 15 different construction companies came to the conference. Directly after the conference, all the companies submitted their bids immediately. What is the next step the project team should take?
After the project manager has collected the requirements and received approval for the scope statement, what process should the project manager do next?
The project manager is working on a new electrical wiring upgrade project for the entire office. Due to safety issues, the project manager cannot move forward with many parts of the project without inspections and permits from the local Buildings Department. Most permits take approximately 6 weeks to get. Where would the project manager document the opportunity the project should take if a permit comes within 2 weeks instead of the 6 weeks?
Senior management in the organization would like your project to have as few risks as possible. Which of the following contracts best meet their criteria?
While planning the risk responses for a construction project, the project manager and project team have decided they will have to choose a new electrical contractor due to the fact that the recommended contractor has legal issues with the local building department. The legal issues could cause the project to be delayed. What risk response does this represent?
A project manager has completed the project status report. The report states the CPI is 1.1 and the SPI is 1.14. The report was given to the project sponsor, who has become very upset about the project’s progress and has requested an immediate meeting with the project manager. What should the project manager report in the meeting?
The project sponsor has signed off on the project charter and has spoken to the project manager, who then has to keep the cost down on the project. The project manager agrees to try his best to keep cost down and to finish the project under budget. What should the project manager do next?
Mark is currently working on the workstation upgrade project. He has noticed there are three activities on the critical path, which are activity A, C, and D. Activity B has a slack of 2 and a duration of 4 days. Activity C has a duration of 3 days, and activity D has a duration of 6 days. What is the slack on activity A?
While measuring quality on a project, the project team decided to just measure the quality as pass/fail. The team has determined that this is the best method because the deliverables are mostly functions that will need to produce a correct result. What best describes this measurement?
While working with the system administrator, the project manager identifies many different types of resources required for the project to be completed successfully. The project manager classifies them as HR, material, equipment, and consumable resources. Where can the project manager best document these resources?
While working on a large multinational project, you identify some of the positive and negative stakeholders. What process group are you currently engaged in?
When managing a small construction project, the project manager has informed the project team members that they are using too many materials to complete the project work. The project manager feels the team members could utilize a lot less materials to accomplish the work they’re currently doing. What process describes this scenario?
The project has just been initiated, and the project sponsor calls the project manager and asks approximately when he thinks the project will be completed. The project manager replies that they have been unable to thoroughly analyze the work needed to complete the project and that he is not very knowledgeable about this kind of work. The sponsor insists on receiving a high-level estimate. The project manager responds that it will take approximately 3 months to complete the work based on his experience working on a project very similar to this one. What technique best represents this estimate?
While working on the workstation upgrade project, the project sponsor informs the team that they have to stop the project immediately and start working on a router upgrade project. The sponsor wants the router upgrade project to start in as little as 2 days. What should the project manager do next?
The project manager has just spoken to one of the software developers, Bill, about the project and has asked for an estimate of how long it will take to code a specific function. Bill said that it would take a maximum of 10 days, but that most likely it will be 6 days. The project manager has calculated the PERT estimated duration of this activity to be 6 days. What is the least amount of days it will take to complete this activity?
You have just been appointed the new project manager on a product upgrade project. One person in particular at the company feels like the project may cause them to lose their job. This person has expert knowledge of the current product and does not feel that it needs an upgrade. What would you consider this person on your project?
While conducting a risk assessment on a project, the project manager has identified a new regulatory risk. If the project is not completed by July 31, the company will have to scrap the project. What best describes this?
The project manager and the team have worked endless hours to calculate the amount of time it will take to conduct each activity. They would like to document some of the assumptions they made and the constraints they may face when the project is executed. What document will they use for this?
While managing the project team the agile project manager is having a very difficult time understanding why team members are always frustrated when communicating with him. What critical soft skills does this project manager lack?
What is the main difference between the product scope and the project scope?
While working on a project, you realize that you will not be able to install the server and the workstations at the same time. In fact, the team has alerted you that after the server installation is done, you should wait an additional 4 days before installing the workstations. This is due to the updates the server will need, which is an automated process. What do you need to add to the schedule in order to account for this delay?
During a new smartphone development project, the customers are given a prototype of the smartphone for them to try. They inform you that the phone constantly reboots, and sometimes the touch screen does not work. What tool can the project team use to find the reasons for these defects?
Managing a project can be a very complex task that involves identifying and managing all the stakeholders on the project. The project manager spends 90% of their time doing what important task?
While developing very complex software, the project manager met with some of the industry’s top subject matter experts to understand their perspectives about solving some of the problems in the software. What tool best describes these meetings?
The project manager is currently reviewing all of the meetings that took place over the past few weeks to ensure that it was done according to the communication management plan. What process is the project manager currently conducting?
When an organization is considering a project, what are some of the factors that can influence why a project should get done?
The project sponsors have informed the project manager that they would like to be included in the weekly meetings along with the team members. What should the project manager update to include the sponsors in the weekly meetings?
While planning a project, the project manager is given many requirements that the customers would like to add to the project. Upon further investigation, the project manager decides that a few of the requirements will not be feasible within the limited time and cost allocated to the project. What document would best list the requirements that will not be added to this project?
The project team is currently working on an advertising project. They have completed a few of the activities, which includes writing the script for the commercial. Once the team completes an activity, what should they do next?
Agile project conduct planning at multiple points in time as the scope is refined and change over the project lifecycle. This is known as?
While working on a complex software development project, the team is having a difficult time understanding a process used to code a particular report. They find the process to have many different paths and if/then scenarios. They have asked the project manager for a tool that can help them see the process on a large white board or on paper. What’s the best tool the project manager can recommend for the team to help visualize the process?
You’re currently working on a large new building development project. The project team is currently breaking down the deliverables listed in the project scope statement into work that is more manageable. What process best describes this scenario?
A team member is working on upgrading the network server while another team member is painting the server room. The outcomes of these two events will not affect each other. What best describes the relationship between these two events?
While building the agile space for new agile team which of the following tools should the project manager insurer is available to all of them?
Which of the following is an XP practice that helps to create a shared vision between the developers and the customers?
The project manager is informed that a manager in the finance department has requested to be included in the weekly status updates on the project. What document should the project manager update immediately?
While attempting to determine the schedule for the project, the project manager has been informed from the team that each line of code will take about 15-45 minutes to write and debug. There will be about 1 million lines of code in the application. What schedule-estimating technique best describes this estimate?
While constructing a roof for a large building, the project team has identified the risk of a snowstorm. Due to the region in the country and the time of the year, the team has decided to take no action or preparations for the snowstorm. What risk response strategy is the team using?
While working on a large utility project for a major metropolitan area, the project manager has noticed that there is no change control board to approve changes for the project. What would be the best step for the project manager to take in this scenario?
While managing a product development project, the project manager met with the team to determine some of the key tasks that will ensure they produce a high-quality product. What should they consider the most important concept in quality?
While compiling all the work performance information into the work performance report, a project manager notices that the SPI of the project is .6 and the CPI is .7. What action should the project manager take next on this project?
The agile project team has decided to do one of the features from the product backlog. The single feature will take six weeks to complete and will be reviewed by the customer. What actions should the agile project manager take next?
While conducting procurement on a project, the project manager has received many different bids with a wide variance of estimated cost for the work. What can the project manager use to best determine which vendor has given a realistic price?
During the datacenter development project, the project manager has noticed that some of the work being done on the project is not in the baseline scope. The project manager has analyzed the work completed by the project team and then compared that to the project management plan to see where the differences are. What process best describes the work of the project manager?
The project team is working with the customers to write the user stories. The customers have refused as they claim this would add no value to the project. What would be the best step to resolve this?
A project manager wants to ensure that the new cell phone the project is creating will beat or match the performance of new cell projects by other companies. What tool would be the best for the project?
Which of the following is not a principle of agile planning?
The project manager is having a difficult time keeping the project on plan. There are many changes regarding the project scope, which has led to an increase in the project budget. Management would like a reason why there have been so many scope changes on this project. What would most likely cause many scope changes on a project?
The project manager has acquired the project team members and is starting to work with them to complete the project work. During this process the project manager has utilized a variety of rewards and recognition theories to keep the team motivated. What is the output of this process?
Senior management has requested an update to the current product upgrade project. The project manager knows she has to keep the information high level and as short as possible. Which resource would be the best to show senior management?
The project team has finished 60% of the deliverables when management informs the project manager that the project will be canceled immediately and the team will be reassigned to work on a new project that management feels is more important. What should the project manager do right away?
The product owner has requested to be showing how much work there remains to be done on the project. What would be the best agile tool to display this?
While developing complex software for an organization, the project team creates a computer-generated model of what it will look like when it is done. This model is given to the customers for their feedback. What best describes this model?
Your company has just started a project to allow remote workers to join the network using a virtual private network (VPN). During the execution of the project, one of the VPN servers completely fails, and the team will need to replace it as soon as possible. Fortunately, the project team anticipated that this might happen and has a plan for replacing the server. What should the project manager do next?
When deciding what user stories should get done in the next iteration what should the project team consider?
When managing risks on a project, the project manager should be aware of the individual project risks and which other project risks?
The project manager has met with the project team and has informed them that his team performance assessments are done, and he would like to speak with each of them individually about the results. What process group is this?
While working on a large project, the project manager originally counted 12 stakeholders. A new requirement and six more stakeholders were added to the project. How many communication channels are on this project?
While planning a major network upgrade project, one stakeholder has given a requirement to upgrade the switches. The project manager has determined that this would be too costly to be included in the project and has decided to exclude it. What process will the project manager use to document this exclusion?
The project manager has just identified a new regulation that can possibly delay the project significantly. The project manager has added this new regulation to the risk register. What should the project manager do next with this risk?
The project team has been brought together for the first time to work on the network upgrade project. They were able to learn about the functions they will doing on the project and what their roles will be. What will the team do next, according to Tuckman’s ladder?
The project manager has taken all the work performance information that has been created so far on the project. He has started to create the overall project status report to present to the project stakeholders. What process is the project manager conducting?
After many years of following the agile principles the project team has implemented a few new methods in addition to the agile methods in order to increase the efficiency of the project. This will be known as?
Over the last three weeks the project team has finally been able to establish a shared vision of what the product would look like when it is complete. This is an example of?
While managing the stakeholders’ engagement, the project manager notices that some of the team members are not respectful to other team members. This has led to a few conflicts between the members. What can the project manager best do about this?
You are currently managing a business process reengineering project and have identified all the risks that can affect the project. You would like to put the risks in order from most impact to least impact on the project. What is the best process for doing so?
The project manager and sponsor are consulting with banks and other lending institutions in order to obtain funds for the project. What process this describes these actions?
The project manager and team are currently working to create a list of activities needed to complete the project. They have come to one particular work package that they cannot decompose because they do not know enough about the work yet. They have decided that midway through the project, they will decompose this particular work package. What tool or technique are they using?
The project manager has noticed that a few team members are having a difficult time following the process to inspect the quality of new software. What is the best tool to help them see the process, making it easier to follow?
While working on an agile project, the sponsor would like to know how much work remains to be completed in the project. The project manager has scheduled a meeting with the sponsor for the next day. What tool would be best for the project manager to take to the meeting?